Need extra care when using plastic shredder
Commissioning:
1. Turn on the power grid switch;
2. Press the jog button to test run the machine;
3. Starting and idling for 1 to 2 weeks;
4. Combined operation of transfer machine and crusher;
5. Check that there is no abnormality, and send out the power-on signal.
6. During operation, the machine and motor must be free of sensation, sound and humidity must be normal, the temperature of each bearing must not exceed 75℃, and the temperature of the motor must not exceed the nameplate rules.
7. The chain tightness of the transfer machine must be the same. Under full load, the chain tightness is not allowed to exceed the length of the two chain links, and there must be no chain jams or chain jumps.
8. After the fusible plugs or explosive discs of the reproduced machine coupling are damaged, they shall not be replaced with wood or other materials.
9. The safety equipment of the protection net of the crusher should be intact, and it should be checked frequently during the operation. If it is damaged, it should be shut down immediately.
10. The safety equipment such as the tail protection of the reprinter must be intact.
11. Transfer and transfer aircraft.
(1) Clean up the floating coal and gangue on the tail, sides of the fuselage and under the bridge;
(2) Protect cables, water pipes and oil pipes and hang them neatly;
(3) Check the roadway support and move the transfer machine while ensuring safety;
(4). The trolley and the tailstock of the belt conveyor should be in good contact with each other, without deviation, and excellent lap after removal to prevent large pieces of plastic from damaging the tape and ensure smooth coal flow;
(5) After transferring the carrier, the nose and tail of the machine must be flat, straight and stable, and the jack rod must be retracted.
Operation attention
1. The plastic shredder and power unit should be installed firmly. If the plastic crusher needs to be fixed for long-term operation, it should be fixed on the cement foundation; if the plastic crusher needs to be movably operated, the unit should be installed on a base made of angle iron, and ensure that the power engine (diesel engine or electric motor) and plastic The pulley groove of the crusher is in the same rotation plane. 2. After the plastic crusher is installed, check the fastening of each fastener, and tighten it if it is loose. At the same time, check whether the belt tightness is appropriate.
3. Before starting the plastic crusher, turn the rotor by hand to check whether the claws, hammers and the rotor are running sensitively and reliably, whether there is any collision in the crushing chamber, and whether the rotation direction of the rotor is consistent with the direction indicated by the arrow of the machine. Is the plastic crusher smooth?
4. Do not change the belt pulley casually, in case the speed is too high to cause the blasting of the crushing chamber, or the speed is too low to affect the operating efficiency of the crusher.
5. After starting the plastic crusher, it should be kept idling for 2~3min first, and no abnormal phenomenon should be observed before feeding into operation.
6. Pay attention to the operation of the plastic crusher at all times during operation. Firstly, the feeding must be even to prevent blocking the crushing chamber; secondly, do not overload the operation for a long time. If there are vibrations, noises, excessive temperature of the bearings and the machine body, or spraying materials, the machine should be shut down immediately for inspection, and the operation can be continued after troubleshooting.